CPEC Projects (Package 2B & Package III)

Geotechnical Investigation and Piling Work

CPEC Projects (Package 2B & Package III)

For the CPEC Package 2B and III, EEA was responsible for drilling more than 100 boreholes and installing over 100 piles at a depth of 30 meters.

The project was part of Pakistan’s collaboration with China on the China-Pakistan Economic Corridor, a strategic infrastructure initiative. EEA’s work ensured the safety and longevity of the project’s bridges and other infrastructure.

Details
Piles installed 100+
Boreholes drilled 12
Location Various Pakistan
Project start 2017
Project finish 2017
Clients FWO ZKB Consultant NESPAK

Bridges in North Waziristan (USAID Funded)

Geotechnical Investigation

Bridges in North Waziristan (USAID Funded)

This project was part of the USAID-funded initiative to rebuild North Waziristan’s infrastructure. EEA performed the geotechnical investigation for several bridges to ensure they could withstand the region’s challenging soil conditions.

The findings helped engineers design resilient structures that could support economic and transportation improvements in the area.

Details
Boreholes drilled 10
Location North Waziristan Pakistan
Project start 2018
Project finish 2018
Client FWO Consultant NESPAK

 

Tajikistan, Afghan, Pakistan, and India Gas Pipeline (TAPI)

Geotechnical Investigation

Tajikistan, Afghan, Pakistan, and India Gas Pipeline (TAPI)

EEA provided geotechnical investigation services for the TAPI gas pipeline, a vital international project spanning multiple countries. The investigation involved drilling 49 boreholes in 2018 to assess the subsoil characteristics across the pipeline route.

This analysis helped ensure the pipeline’s stability across diverse terrains, contributing to a significant energy project connecting Central and South Asia.

Details
Boreholes drilled 49
Location Multiple regions in Pakistan
Project start 2018
Project finish 2018
Client Decon Company
×